NewsPress ReleasesProperty DevelopmentLuma22 January 2024 update for Luma22 project February 1, 2024 FacebookTwitterWhatsApp External plaster 90% | False ceiling 70% | Floor tiles on all floors 75% | Lift installation 15% | Roof waterproofing 75% | Roof Electromechanical works 30% | Swimming pool works startedConstruction progress is on track. .