1st Podium Slab in Progress
External plaster 100% | False ceiling 80% | Floor tiles 90% | Lift installation 80% | Roof waterproofing 90% | Roof electromechanical works 60% | Swimming pool 15% | Aluminium works 20% | Joinery works 20% | Construction progress is on track.
Excavation works 80 | Pile head breaking 80% | PCC 50% | Pile caps 30% | Ground floor verticals 10% | Construction progress is on track
External plaster 90% | False ceiling 70% | Floor tiles on all floors 75% | Lift installation 15% | Roof waterproofing 75% | Roof Electromechanical works 30% | Swimming pool works started
Construction progress is on track.
.
Excavation works 50% | Pile head breaking 50% | Pile testing completed | PCC started
Construction progress is on track.
Floor tiles on all floors 50% | Plaster works on all floors 100% | False ceiling 50% | Roof waterproofing 50% | External plaster 50% | Construction progress is on track