March 2024 update for Luma22

Internal Finishes 85% | External Finishes 60% | MEP works 90


February 2024 update for Luma22

External plaster 100% | False ceiling 80% | Floor tiles 90% | Lift installation 80% | Roof waterproofing 90% | Roof electromechanical works 60% | Swimming pool 15% | Aluminium works 20% | Joinery works 20% | Construction progress is on track.

February 2024 update for Luma Park Views

Excavation works 80 | Pile head breaking 80% | PCC 50% | Pile caps 30% | Ground floor verticals 10% | Construction progress is on track

January 2024 update for Luma22 project

External plaster 90% | False ceiling 70% | Floor tiles on all floors 75% | Lift installation 15% | Roof waterproofing 75% | Roof Electromechanical works 30% | Swimming pool works started
Construction progress is on track.

.

January 2024 update for Luma Park Views project

Excavation works 50% | Pile head breaking 50% | Pile testing completed | PCC started
Construction progress is on track.

December 2023 update for Luma Park Views

Piling works completed | Construction progress is on track

December 2023 update for Luma 22

Floor tiles on all floors 50% | Plaster works on all floors 100% | False ceiling 50% | Roof waterproofing 50% | External plaster 50% | Construction progress is on track