Piling works completed | Construction progress is on track
December 2023 update for Luma 22
Floor tiles on all floors 50% | Plaster works on all floors 100% | False ceiling 50% | Roof waterproofing 50% | External plaster 50% | Construction progress is on track
October 2023 Luma22 update
-Concrete casting works in all floors 100%
-Block works for 2nd and 3rd floors 100%
-Plaster works for 1st & 2nd floors 100%
The gym in the middle of the garden is now visible.