October 2020 Easy19 Construction Update

  • Steel work bottom mesh & top mesh along grid lines (A-J) (10-14) and Completed all beams and ramp area.
  • Post Tension along grid lines (1-7) (A-J) laying one direction of completed along grid lines (A-J) (7-14).
  • Cast Concrete (screed) rear side and left & right and half front side.
  • Arrange material and housekeeping.
  • Steel work complete laying top mesh along gridlines (A-E) (1-14) and finishing the ramp area.
  • Start Back Filling.
  • Electrical- Ground SlabPVC Piping.
  • Plumbing- Ground Slab Sleeve Fixing.