- Steel work bottom mesh & top mesh along grid lines (A-J) (10-14) and Completed all beams and ramp area.
- Post Tension along grid lines (1-7) (A-J) laying one direction of completed along grid lines (A-J) (7-14).
- Cast Concrete (screed) rear side and left & right and half front side.
- Arrange material and housekeeping.
- Steel work complete laying top mesh along gridlines (A-E) (1-14) and finishing the ramp area.
- Start Back Filling.
- Electrical- Ground SlabPVC Piping.
- Plumbing- Ground Slab Sleeve Fixing.