November 2020 Easy19 Construction Update

  • Formwork- laying panels for 2nd slad.
  • Post Tension marking for the 2nd slab and cutting anchors for 2nd slab.
  • Closing the tendons area openings.
  • Electrical- 1F Slab marking and Store Setting.
  • Housekeeping on going on daily basis.